Casco Bay Ferry Terminal Rehabilitation Great Diamond Island, ME

Casco Bay Ferry Terminal Rehabilitation Great Diamond Island, ME

Island, Maine

Bancroft Contracting Corporation was selected to be the General Contractor for the rehabilitation of Casco Bay Lines’ Ferry Terminal located on Chebeague Island in the Casco Bay, facilitated by the State of Maine Department of Transportation. This project involved the removal and replacement of key structural support systems for the pier.

Several years of use had deteriorated structural components of Great Diamond Island’s ferry terminal. After major storms in Winter 2023, these weaknesses were made worse and the pier required a major overhaul that included:

Installation of (9) 50 ft.-long Pressure Treated Timber Piles

  • These piles were set into place with a barge crane, driven into mud using a vibratory hammer, and finally driven to a design depth with a diesel pile driver.

Removal and Replacement of (2,500) BF of Pressure Treated 4×8 Heavy Timber Cross-Bracing

  • This work involved careful planning around the tide cycle as several of the timbers were just above the low-water level.

Installation of New Electrical Service and Exterior Lighting Improvements

  • Working with a local Electrical Subcontractor and Central Maine Power, Bancroft Contracting installed new light poles for the pier using timber piles.

Removal and Replacement of (4,000) SF of Pressure Treated 4×8 Deck Boards

  • A large part of this project involved replacing the entire deck of the pier at Great Diamond Island. This work was done in segments.

During the construction process, crews encountered some environmental challenges. But, with careful planning and constant communication with the Engineer of Record, these challenges were worked through, and the work was completed. All while the Casco Bay Ferry traffic continued uninterrupted. With these repairs, the structural integrity of this pier has been improved significantly.

CONTRACT AMOUNT: $2.4M
DATE OF COMPLETION: Summer 2025
ENGINEER: Stantec

Related Projects

4/19/2024 At the new home of the Crane and Rigging

4/19/2024 At the new home of the Crane and Rigging Division Laydown Yard in South Paris, 5 cranes were prepped and assembled for OSHA inspections. With flying colors, the Liebherr

4/21/2023 It couldn’t come soon enough for the weather-hardened crew

4/21/2023 It couldn’t come soon enough for the weather-hardened crew at Middle Dam to finish up for the winter season and turn their taillights to the project. This winter’s scope

6/28/2024 After reporting on Bancroft24 and its voyage up to

6/28/2024 After reporting on Bancroft24 and its voyage up to Maine, it felt appropriate to continue the narrative on Bancroft’s Marine Division as things are really starting to take shape

7/26/2024 Bancroft Contracting’s Marine Division has successfully completed and put

7/26/2024 Bancroft Contracting’s Marine Division has successfully completed and put the first job in the books! D. Stetson Services approached Bancroft with the need to get this work done quickly,

Scroll to Top